Airport Construction & Development

Airport Construction & Development

Airport Improvement Guidelines

Download PDF (Large File - 17 MB)

Exterior Improvement Concepts & Guidelines

Download PDF

Current Projects

RUNWAY 16R-34L & EAST ALV IMPROVEMENTS (RNO)

Project Description:

Reconstruction of existing Runway 16R-34L concrete pavement, asphalt blast pads, and asphalt shoulders, replacement of runway approach lighting system, and east airfield lighting vault (ALV).

Current Phase:

Phase 2 (RWY 16R)

Design Services Awarded:

May 2018

Design Cost:

$4,095,000.00

Design Consultant:

Wood Rodgers

Sealed Proposals Opened:

Bids Opened 2/4/2020

Construction Cost:

$42,736,928.00

Contractor:

Granite Construction

Anticipated Completion Date:

November 2022

 
VALE GRANT eGSE CHARGING STATIONS (RNO)

Project Description:

The Airport Authority is installing electric charging stations at RNO with the commitment from the various airlines to replace petroleum-based ground support equipment (GSE) with electric ground support equipment (eGSE). The installation of electric chargers and the conversion to eGSE by the airlines will significantly reduce criteria pollutants, such as ozone, carbon monoxide (CO), and particulate matter (PM). Ozone is formed by the chemical interaction between oxides of nitrogen (NOx) and volatile organic compounds (VOCs).

Current Phase:

Construction

Design Services Awarded:

July 2020

Design Cost:

$26,285.00 (Feasibility Study and Design)

Design Consultant:

Dinter Engineering

Sealed Proposals Opened:

May 2020

Construction Cost:

$1,009,468.00

Contractor:

Helix Electric of Nevada

Anticipated Completion Date:

June 2021

 
AIRFIELD WILDLIFE HAZARD MANAGEMENT (RNO)

Project Description:

The RNO Airfield Wildlife Hazard Management Project will involve the land application of a six-inch thick, three-inch minus gravel and crushed stone aggregate (gravel) material. Approximately 302,440 square yards of RNO's Air Operations Area (AOA) would be covered with the gravel material. The gravel material will be placed west of Taxiway A between the ARFF and the south end of Taxiway A (approximately 250 feet in width), and south and east of the ends of Runway 16R and Taxiways A and B to the Boynton Slough (Dry Creek).

Current Phase:

Construction (included in the Runway 16R/34L Reconstruction Project)

Design Services Awarded:

December 2018

Design Cost:

$179,000.00

Design Consultant:

Wood Rodgers

Sealed Proposals Opened:

February 2020

Construction Cost:

$1,927,927.00

Contractor:

Granite Construction

Anticipated Completion Date:

November 2021

 
TAXIWAY A AND AIRCRAFT APRON RECONSTRUCTION-DESIGN (RTS)

Project Description:

Design of the Reconstruction of Taxiway "A" and adjoining acraft apron, electrical upgrates and striping.

Current Phase:

Phase 2 Construction (FAA Phase 3)

Design Services Awarded:

March 2020

Design Cost:

$1,088,382.00

Design Consultant:

Kimley-Horn and Associates, Inc.

Sealed Proposals Opened:

March 2021

Construction Cost:

$3,256,256.00

Contractor:

Granite Construction 

Anticipated Completion Date:

October 2021

 
PASSENGER BOARDING BRIDGE REPLACEMENT - PHASE 2 (RNO)

Project Description:

Replacement of five (5) passenger boarding bridges located at gates B4, B6, B8, B9 and C11.

Current Phase:

Construction

Design Services Awarded:

May 2020

Design Cost:

$328,335.00

Design Consultant:

AERO Systems Engineering, Inc.

Sealed Proposals Opened:

October 2020

Construction Cost:

$3,609,570.00

Contractor:

John Bean Technologies Corporation

Anticipated Completion Date:

July 2021

 
SKYBRIDGE ESCALATOR MODERNIZATION (RNO)

Project Description:

Modernize two (2) escalators, which serve the skybridge leading to the parking garage. Leaving the existing escalator backbone in place and installing modular units. 

Current Phase:

Bidding 

Design Services Awarded:

September 2021

Design Cost:

$58,000.00

Design Consultant:

HK Architects

Sealed Proposals Opened:

June 2021

Construction Cost:

TBD

Contractor:

TBD

Anticipated Completion Date:

TBD

 
TWY B/M RECONSTRUCTION & GA RUNUP AREAS PROJECT (RNO)

Project Description:

Reconstruct segment of TWY B on either side of 7-25, Reconstruct TWY M, construct two new GA runup area along TWY C. 

Current Phase:

Designer Selection 

Design Services Awarded:

June 2021

Design Cost:

TBD

Design Consultant:

TBD

Sealed Proposals Opened:

TBD

Construction Cost:

TBD

Contractor:

TBD

Anticipated Completion Date:

TBD

 
TICKETING HALL EXPANSION CMAR (RNO)

Project Description:

Expansion of Ticketing Hall Area via Construction Manager at Risk

Current Phase:

CMAR-Designer Selection 

Design Services Awarded:

July 2021

Design Cost:

TBD

Design Consultant:

TBD

Sealed Proposals Opened:

TBD

Construction Cost:

TBD

Contractor:

TBD

Anticipated Completion Date:

TBD

 
Customer Feedback