Airport Construction & Development

Airport Construction & Development

Airport Improvement Guidelines

Download PDF (Large File - 17 MB)

Current Projects

RUNWAY 16R-34L & EAST ALV IMPROVEMENTS (RNO)

Project Description:

Reconstruction of existing Runway 16R-34L concrete pavement, asphalt blast pads, and asphalt shoulders, replacement of runway approach lighting system, and east airfield lighting vault (ALV).

Current Phase:

Phase 2 (RWY 16R)

Design Services Awarded:

May 2018

Design Cost:

$4,095,000.00

Design Consultant:

Wood Rodgers

Sealed Proposals Opened:

Bids Opened 2/4/2020

Construction Cost:

$42,736,928.00

Contractor:

Granite Construction

Anticipated Completion Date:

November 2021

 
TERMINAL ELEVATOR MODERNIZATION AND NEW ELEVATOR INSTALLATION (RNO)

Project Description:

Modernization of four (4) existing elevators and construct one (1) new elevator in RNO Terminal Building.

Current Phase:

Construction

Design Services Awarded:

June 2018

Design Cost:

$384,500.00

Design Consultant:

Vertical Transportation Excellence

Sealed Proposals Opened:

June 2019

Construction Cost:

$1,897,370.00

Contractor:

Q&D Construction

Anticipated Completion Date:

July 2020

 
PASSENGER BOARDING BRIDGE REPLACEMENT (RNO)

Project Description:

Replacement of six (6) passenger boarding bridges located at gates B10, B11, C1, C3, C5, C7, and replacement of walkway at gate B10.

Current Phase:

Construction

Design Services Awarded:

June 2018

Design Cost:

$429,415.00

Design Consultant:

AERO Systems Engineering, Inc.

Sealed Proposals Opened:

September 2019

Construction Cost:

$4,584,288.00

Contractor:

John Bean Technologies Corporation

Anticipated Completion Date:

July 2020

 
VALE GRANT eGSE CHARGING STATIONS (RNO)

Project Description:

The Airport Authority is installing electric charging stations at RNO with the commitment from the various airlines to replace petroleum-based ground support equipment (GSE) with electric ground support equipment (eGSE). The installation of electric chargers and the conversion to eGSE by the airlines will significantly reduce criteria pollutants, such as ozone, carbon monoxide (CO), and particulate matter (PM). Ozone is formed by the chemical interaction between oxides of nitrogen (NOx) and volatile organic compounds (VOCs).

Current Phase:

Design

Design Services Awarded:

July 2020

Design Cost:

$26,285.00 (Feasability Study and Design)

Design Consultant:

Dinter Engineering

Sealed Proposals Opened:

May 2020

Construction Cost:

$1,009,468.00

Contractor:

Helix Electric of Nevada

Anticipated Completion Date:

April 2021

 
AIRFIELD WILDLIFE HAZARD MANAGEMENT (RNO)

Project Description:

The RNO Airfield Wildlife Hazard Management Project will involve the land application of a six-inch thick, three-inch minus gravel and crushed stone aggregate (gravel) material. Approximately 302,440 square yards of RNO's Air Operations Area (AOA) would be covered with the gravel material. The gravel material will be placed west of Taxiway A between the ARFF and the south end of Taxiway A (approximately 250 feet in width), and south and east of the ends of Runway 16R and Taxiways A and B to the Boynton Slough (Dry Creek).

Current Phase:

Construction (included in the Runway 16R/34L Reconstruction Project)

Design Services Awarded:

December 2018

Design Cost:

$179,000.00

Design Consultant:

Wood Rodgers

Sealed Proposals Opened:

February 2020

Construction Cost:

$1,927,927.00

Contractor:

Granite Construction

Anticipated Completion Date:

November 2021

 
TAXIWAY A AND AIRCRAFT APRON RECONSTRUCTION-DESIGN (RTS)

Project Description:

Design of the Reconstruction of Taxiway "A" and adjoining acraft apron, electrical upgrates and striping.

Current Phase:

Bids Opened

Design Services Awarded:

March 2020

Design Cost:

$1,088,382.00

Design Consultant:

Kimley-Horn and Associates, Inc.

Sealed Proposals Opened:

May 2020

Construction Cost:

$4,636,636.00

Contractor:

Road & Highway Builders

Anticipated Completion Date:

TBD

 
PASSENGER BOARDING BRIDGE REPLACEMENT - PHASE 2 (RNO)

Project Description:

Replacement of five (5) passenger boarding bridges located at gates B4, B6, B8, B9 and C11.

Current Phase:

Design

Design Services Awarded:

May 2020

Design Cost:

$328,335.00

Design Consultant:

AERO Systems Engineering, Inc.

Sealed Proposals Opened:

TBD

Construction Cost:

TBD

Contractor:

TBD

Anticipated Completion Date:

TBD

 
LANDSIDE PAVEMENT MANAGEMENT (RNO)

Project Description:

The project scope consists of providing maintenance operations that include, but are not limited to: pavement preparation, placement of 647,438 square feet Type II Micro surfacing (slurry sealing), installing pavement markings, and placing and maintaining traffic control.

Current Phase:

Construction

Design Services Awarded:

N/A

Design Cost:

N/A

Design Consultant:

RTAA

Sealed Proposals Opened:

June 2020

Construction Cost:

$222,222.00

Contractor:

Intermountain Slurry Seal Inc.

Anticipated Completion Date:

September 2020

 

Customer Feedback