Current Projects

RUNWAY 16R-34L & EAST ALV IMPROVEMENTS (RNO)

Project Description:

Reconstruction of existing Runway 16R-34L concrete pavement, asphalt blast pads, and asphalt shoulders, replacement of runway approach lighting system, and east airfield lighting vault (ALV).

Current Phase:

Phase 2 (RWY 16R)

Design Services Awarded:

May 2018

Design Cost:

$4,095,000.00

Design Consultant:

Wood Rodgers

Sealed Proposals Opened:

Bids Opened 2/4/2020

Construction Cost:

$42,736,928.00

Contractor:

Granite Construction

Anticipated Completion Date:

November 2022

 
TERMINAL LOOP ROAD RECONSTRUCTION (RNO)

Project Description:

Design & Reconstruction of PCC portion of Terminal Loop Road, ADA, and Pedestrain/Terminl Safety Improvements

Current Phase:

Design 

Design Services Awarded:

10/14/2021

Design Cost:

$998,669.00

Design Consultant:

Kimley-Horn

Sealed Proposals Opened:

09/02/2021

Construction Cost:

TBD

Contractor:

TBD

Anticipated Completion Date:

TBD

 
BLUE LOT PARKING LOT RECONSTRUCTION (RNO)

Project Description:

Design & Reconstruction of the Blue Lot Parking Lot 

Current Phase:

Designer Selection 

Design Services Awarded:

November 2021

Design Cost:

$121,900.00

Design Consultant:

Kimley-Horn 

Sealed Proposals Opened:

04/21/2022

Construction Cost:

$2,136,277.00

Contractor:

Sierra Nevada Construction 

Anticipated Completion Date:

July 2022

 
TAXIWAY A AND AIRCRAFT APRON RECONSTRUCTION-DESIGN (RTS)

Project Description:

Design of the Reconstruction of Taxiway "A" and adjoining aircraft apron, electrical upgrades, and striping. Project being built over multiple years due to FAA Funding. 

Current Phase:

Phase 3 Construction 

Design Services Awarded:

March 2020

Design Cost:

$1,088,382.00

Design Consultant:

Kimley-Horn 

Sealed Proposals Opened:

02/24/2022

Construction Cost:

$3,362,499.00

Contractor:

Granite Construction 

Anticipated Completion Date:

November 2022

 
AIR CARGO WAY LIFT STATION IMPROVEMENTS (RNO)

Project Description:

Design & Reconstruction of Air Cargo Way Lift Station

Current Phase:

Design

Design Services Awarded:

09/09/2021

Design Cost:

$71,000.00

Design Consultant:

Shaw Engineering

Sealed Proposals Opened:

02/24/2022

Construction Cost:

$749,400.00

Contractor:

Farr Construction 

Anticipated Completion Date:

December 2022

 
TWY B/M RECONSTRUCTION & GA RUNUP AREAS PROJECT (RNO)

Project Description:

Reconstruct segment of TWY B on either side of 7-25, Reconstruct TWY M, construct two new GA runup area along TWY C. 

Current Phase:

Design

Design Services Awarded:

June 2021

Design Cost:

$430,732.00

Design Consultant:

Wood Rodgers

Sealed Proposals Opened:

05/14/2021

Construction Cost:

TBD

Contractor:

TBD

Anticipated Completion Date:

TBD

 
TICKETING HALL EXPANSION CMAR (RNO)

Project Description:

Expansion of Ticketing Hall Area via Construction Manager at Risk

Current Phase:

CMAR-Design

Design Services Awarded:

July 2021

Design Cost: $2,202,821.00

Design Consultant:

RS&H

CMAR PreConstruction Services Awarded:

10/14/2021

CMAR PreConstruction Cost:

$300,000.00

CMAR:

McCarthy Building Companies

Sealed Propsal Opened:

08/16/2021

CMAR Construction Cost: TBD

Contractor:

TBD

Anticipated Completion Date:

TBD

TERMINAL LIFT STATION IMPROVEMENTS (RNO)

Project Description:

Design & Construction of Terminal Lift Station  

Current Phase:

Design

Design Services Awarded:

August 2021

Design Cost:

$34,200.00

Design Consultant:

Shaw Engineering

Sealed Proposals Opened:

TBD

Construction Cost:

TBD

Contractor:

TBD

Anticipated Completion Date:

TBD

 