RNO Master Plan: Project 3

Project 3:  Terminal Development – Ticketing Hall Improvements

Project Description

The Ticketing Hall Improvements project was originally scoped to address service level and functional deficiencies in the Ticketing Hall of the Reno-Tahoe International Airport. Issues identified include:

  • Narrowness of the existing passenger circulation hallway,
  • Inadequate space allocated to airline queues during peak departure times,
  • Lack of public restrooms,
  • Confusing wayfinding due to existing signage and limited line-of-sight through the Hall,
  • Lack of available tenant space to lease to existing or future airlines, and the
  • Remaining useful life of a number of building systems.

These existing conditions were expected to be further exacerbated by the passenger growth forecast in the 2018 RNO Airport Master Plan Update.

Existing Ticket Hall Floor Plan
(Click image to see larger version.)

Detailed Planning Study: In December 2020, a Detailed Planning Study was completed. The Detailed Planning Study identified a preferred alternate for improvements to the Ticketing Hall to address the deficiencies identified in the 2018 RNO Airport Master Plan Update. The Detailed Planning Study project team included H+K Architects, HOK, Wood Rodgers, Hyytinen Engineering, Ainsworth Associates, PK Electrical, and OCMI.  Stakeholders, in addition to the RTAA Board of Trustees and RTAA staff, included RNO airline partners (corporate and local) and other Ticketing Hall tenants (ABM, SAS, and TSA).

The preferred alternate for the Ticketing Hall Improvements includes a westerly expansion of the building to the existing roof-line, adding approximately 10,000 square feet to the Ticketing Hall. The preferred alternate has the potential to dramatically and positively change the passenger experience, by moving the circulation hallway and seating into the new frontage, thereby allowing airline ticketing functions to expand into the area currently utilized for circulation. Additional space and volume will be created by removing the floating clouds, relocating the lighting and some of the overhead utilities, and removing the feature walls enclosing the structural braces.  The preferred alternate:

  • Provides new restrooms for passengers on the direct path from ticketing/bag drop off to security.
  • Increases overall airline queuing by 43%.
  • Creates a new 15-foot circulation hallway at the front of the building.
  • Provides similar sized and situated relocation spaces for existing tenants and better protection from the elements for sky cap services.
  • Repurposes the existing circulation hallway to serve as flex space, which, depending on need, could act as a secondary circulation path, queuing for self-check self-tag kiosks, or overflow airline queuing.
  • Identifies an area for touchless vending machines.
  • Provides higher ceilings, longer and better line-of-sight through the hall and introduces more natural daylight into the space.

Current Phase (Design): In July 2021, the RTAA Board of Trustees approved a design contract to RS&H Nevada.  Subsequently, in October 2021, the RTAA Board of Trustees approved Pre-Construction Services for a Construction Manager at Risk contract to McCarthy Building Companies, Inc.  The full Design project team also includes Atkins, Wood Rodgers, Ainsworth Associates, PK Electrical, M Lee Corp, and Selbert Perkins Design. 

Updates on the project are provided at regularly scheduled RTAA Planning & Construction Committee meetings.

Concept 1 - View 1
(Click image to see larger version.)

Concept 2 - View 2
(Click image to see larger version.)

Concept 1 & 2 - View 3
(Click image to see larger version.)

Concept 1 & 2 - View 4
(Click image to see larger version.)

Primary Contacts:

  • Design/Construction Amanda Twitchell, Senior Project Manager
  • Planning Study - Lissa Butterfield, Manager of Planning & Environmental Services

Delivery Method: Construction Manager At Risk (CMAR)

Project Completion Date (Anticipated): Fall 2023

Total Project Cost (Estimate): $20 M

Funding Sources:

  • Design: RTAA Capital Projects Budget Fiscal Year FY21-22
  • Construction: RTAA Capital Projects Budget Fiscal Year FY22-23
  • Detailed Planning Study: Passenger Facility Charge Funding (100%)
CONTRACTS Planning Design CMAR
Pre-Construction
CM
Pre-Construction
Construction
Work

PM/CM
Construction

Vendor H+K Architects RS&H McCarthy Building
Companies, Inc.
Atkins TBD TBD
Award January 2020 July 2021 October 2021 October 2021 September 2022 September 2022
Completion December 2020 July 2022 August 2022 August 2022 October 2023 October 2023
Cost Estimates $220,000 $2,205,821 $300,000 $39,080 $15,900,000 Est. $1,360,000

 